Part # PSU2#1

Part Description: V-Block Clamps

Quantity Req.: Three part numbers/various lot sizes

Name _______________________ Date: _____________

PLEASE HAVE YOUR INSTRUCTOR INITIAL AND DATE THE GREY BOXES (*) AFTER THE REQUIRED OPERATIONS.
Click here to view the part specification.

Step# Location  Description  Initials  Date
10 Instructor Secure the stock from the instructor. *  
20 Bench Layout both clamps on one piece of metal as shown on the print.  
30 Bench Layout 5/16 drill holes as shown in the stock layout.  These are to be used for blade clearance.
40 Bench Center the punch hole locations.
50 Drill Press Center the drill and drill 5/16 holes.
60 Vertical Band Saw Setup saw for cutting clamps.
70 Instructor Have your instructor check setup. *  
80 Vertical Band Saw Saw out the clamps as close as possible without touching the layout lines.  
90 Bench Deburr but DO NOT clean off layout.
100 Bench Inspect parts and turn in your work for grading.